The high pressure blowers are an optional accessory. If you did not order the high
pressure blowers it is still necessary to route the blower cables to the junction box. To
route the cables from the junction box to the blowers refer to “Attaching the Blower
Cables” on page 3-25.
1
Route each blower cable (P/N 76950315) from the CPI through the designated
power pit conduit, through the pit, and out of the pit as shown.
Note: Be sure to keep the power and communications cables in different pit
conduits.
2
From the pit, route both cables into the junction box.
Figure 2-29: Route the Blower Cables
PD032B
CPI
dyno
electronics
route power cables
in designated conduit