I N S T A L L A T I O N
Routing Cables
Version 2
Model 200iP/250iP Motorcycle Pit Dynamometer Installation Guide
2-19
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
ROUTING CABLES
The following instructions show the support arm and control panel mounted on the
right side of the dyno with the Control Panel Interface (CPI) and dyno electronics on
the left side of the dyno.
The CPI and dyno electronics must be placed near the conduits in the pit.
Be sure to keep the power and communications cables in different pit conduits. For
the following instructions, we will designate the pit conduits as shown in Figure 2-21.
Figure 2-21: Pit Dyno Room Layout
PD026A
dyno
electronics
control panel
interface
(CPI)
control panel
junction box
monitor support and tray
route communications cables
in designated conduit
route power cables
in designated conduit