Initial start-up
The initial start-up is carried out during the initial installation. The entire
system is flushed before guard column and separation column are instal-
led.
Caution
The separation column and guard column may not be installed for the
initial start-up.
Make sure that the 6.2744.040 coupling is being used instead of the
columns.
Perform the following steps during the initial start-up:
1 Preparing the software
■
Start the PC program MagIC Net.
■
Open the Equilibration tab in MagIC Net.
■
Select (or create) a suitable method.
2 Preparing the instrument
■
Ensure that the eluent aspiration tubing is immersed in the eluent
and that there is enough eluent in the eluent bottle.
■
Switch on the instrument.
3 Deaerating the high pressure pump
■
Deaerate the high pressure pump(s) via the purge valve (see
Chapter 3.12.3, page 41).