Operational Tests

Power-up
Several tests run at power up. Results are displayed

only if a test fails. The results are displayed to the

right of the test as shown in Figure 13. To display test

screen regardless of results, press any key while press-

ing the ON key at initial power up. If any test fails,

check the troubleshooting section for possible correc-

tion. When displaying the tests as described above, a

stuck key will be indicated.

“Firmware Rev” checks the rev date of the installed

firmware. NVRam, ROM, EEprom, and RAM check

the memory for valid contents. A/D, Tempr, and PLL

check for proper circuit operation. Stuck_keys checks

for any keys that are pressed at power up.
Figure 13 Power-up Test

Battery Test
The battery test checks the output voltage of the bat-

teries. The result is displayed in a simulated analog

meter with the value at the top of the display. The

scale is set from 6-8V. If the voltage is less than 7V,

the batteries should be changed.

Note:

The AT-800 will shut off if the bat-

tery is low, but it will maintain full accuracy at

any battery voltage.

Firmware Rev:

10MAR94

NVRam:
Rom:
EEprom:
Ram:
A/D:
Tempr:
PLL:
Stuck Keys:

Pass
Pass
Pass
Pass
Pass
Pass
Pass

00000000