Commissioning Preparations Chapter 3
Pre-Commissioning Responsibilities
The customer must complete the pre-commissioning checklist; refer to the
Publication
checklist, as well as sign-off dates and signatures indicating completion of the
required tasks.
Commissioning Preparation
The following section identifies all the tools and resources required to
successfully commission a PowerFlex 7000 ‘B’ Frame drive. In addition, it
identifies how to obtain the required equipment in the event that it is not readily
available prior to commissioning the drive. It is recommended that all items listed
below be obtained prior to attempting to commission the drive. The contents of
this section must be reviewed and that the uses of the equipment described
within are understood prior to commissioning of the drive. If support or
additional information is required, contact your local Rockwell Automation
service office or Medium Voltage Support at (519) 740-4790.
Recommended Tools and Equipment
Hand Tools
•
Metric and Imperial wrenches, sockets, and Hex keys
•
Torque wrench
•
Assortment of screw drivers
•
Assortment of electrical tools (wire strippers, electrical tape, crimpers, etc.)
Electrical Equipment
•
High voltage gloves – 10 kV insulation rating (minimum)
•
Approved high voltage potential tester – 10 kV rating (minimum)
•
Anti-static strap
Test Equipment
•
100 MHz or higher oscilloscope with at least two channels and memory
•
600V (1000V rating) digital multimeter with assorted clip leads
•
Megohmmeter with selectable voltage 2500/5000V