A - commissioning, Commissioning, Appendix – Rockwell Automation 7000A PowerFlex Medium Voltage AC Drive (A Frame) - ForGe Control (PanelView 550) User Manual
Page 185
Appendix
A
7000 “A” Frame
7000A-UM151D-EN-P – March 2013
Commissioning
Start-up will be performed at the customer's site. Rockwell
Automation requests a minimum of four- (4) weeks notice to
schedule each start-up.
The standard Rockwell Automation work hours are between 9:00
AM to 5:00 PM EST, (8 hr/day) Monday through Friday, not
including observed holidays. Additional working hours are available
on a time and material basis.
Rockwell Automation recommends the following:
Drive
Commissioning
1.
A pre-installation meeting/conference call with the customer to
review:
– The Rockwell Automation Start-up Plan
–
The
Start-up
Schedule
– The Drive(s) installation requirements
2.
Inspect the drive’s mechanical and electrical devices.
3.
Perform a tug test on all internal connections within the drive
and verify wiring.
4.
Verify critical mechanical connections for proper torque
requirements.
5.
Verify and adjust mechanical interlocks for permanent
location.
6.
Confirm all inter-sectional wiring is connected properly.
7.
Re-verify control wiring from any external control devices
such as PLCs, etc.
8.
Confirm cooling system is operational.
9.
Verification of proper phasing from isolation transformer to
drive.
10.
Confirm cabling of drive to motor, isolation transformer and
line feed.
11.
Collect test reports indicating megger / hipot test has been
performed on line and motor cables.
12.
Control power checks to verify all system inputs such as
starts/stops, faults, and other remote inputs.
Start-up Commissioning
Services