beautypg.com

A - commissioning, Commissioning, Appendix – Rockwell Automation 7000A PowerFlex Medium Voltage AC Drive (A Frame) - ForGe Control (PanelView 550) User Manual

Page 185

background image

Appendix

A

7000 “A” Frame

7000A-UM151D-EN-P – March 2013


Commissioning



Start-up will be performed at the customer's site. Rockwell

Automation requests a minimum of four- (4) weeks notice to
schedule each start-up.


The standard Rockwell Automation work hours are between 9:00
AM to 5:00 PM EST, (8 hr/day) Monday through Friday, not
including observed holidays. Additional working hours are available
on a time and material basis.


Rockwell Automation recommends the following:

Drive

Commissioning


1.

A pre-installation meeting/conference call with the customer to
review:

– The Rockwell Automation Start-up Plan

The

Start-up

Schedule

– The Drive(s) installation requirements

2.

Inspect the drive’s mechanical and electrical devices.

3.

Perform a tug test on all internal connections within the drive

and verify wiring.

4.

Verify critical mechanical connections for proper torque

requirements.

5.

Verify and adjust mechanical interlocks for permanent

location.

6.

Confirm all inter-sectional wiring is connected properly.

7.

Re-verify control wiring from any external control devices

such as PLCs, etc.

8.

Confirm cooling system is operational.

9.

Verification of proper phasing from isolation transformer to

drive.

10.

Confirm cabling of drive to motor, isolation transformer and

line feed.

11.

Collect test reports indicating megger / hipot test has been

performed on line and motor cables.

12.

Control power checks to verify all system inputs such as

starts/stops, faults, and other remote inputs.

Start-up Commissioning

Services