Ii. boiler assembly – Burnham 8H User Manual
Page 8
8
II. Boiler Assembly
A.
Remove Crate
1. Remove all fasteners at crate skid.
2. Lift outside container and remove with all other
inside protective spacers and bracing.
B.
Remove boiler from skid. See Figure 2. Exercise care
to avoid dropping boiler.
1. Place boiler in approximate location. Refer to
Section I: Pre-Installation. Remove base hold down
bolts.
2. Using pry bar under rear corner of Base End Panel,
raise boiler and install 1½” wood blocks under rear
corners. Install ¾” pipe roller between Base and
skid.
3. Remove 1½” wood blocks. Place 3” pipe roller on
floor behind skid.
4. Roll boiler off skid. Move skid out of way.
5. Roll boiler until 3” roller is located as shown. Use
pry bar to install wood blocks under front corners of
base. Remove 3” roller.
Figure 2: Skid Removal
Tapping
Size
Purpose
A
2”
Supply
B
2”
Return
C
3/4”
Relief Valve
D
3/4”
Limit
E
3/4”
Auxiliary Limit
F
3/4”
Washout
G
3/4”
Drain
Table 3: Purpose of Tappings
Figure 3: Tapping Locations
- 81433101R16-1/10 (40 pages)
- Gas-Fired (4 pages)
- Independence IN8 (1 page)
- Independence IN9 (92 pages)
- ALP105 (100 pages)
- 53A (22 pages)
- CHG150 (72 pages)
- Series 2B (52 pages)
- LEDV-3 (1 page)
- ALP399 (3 pages)
- MST513 (4 pages)
- HF SERIES (28 pages)
- SL AL119SL (1 page)
- PVG (64 pages)
- Independence PV (6 pages)
- V9A (64 pages)
- SERIES 3 1099-01R1-/10 (8 pages)
- RSA (52 pages)
- E4 (8 pages)
- SCG 1100-H4 (96 pages)
- SERIES 2 (6 pages)
- MEGASTEAM MST396 (68 pages)
- V7 SERIES (47 pages)
- V9 (4 pages)
- LE L7248 (28 pages)
- LEDV SERIES (36 pages)
- MST396 (64 pages)
- ES2 (52 pages)
- ALP080 (7 pages)
- Minuteman II (6 pages)
- PVG & SCG (4 pages)
- V8 Series (100 pages)
- FCM120 (80 pages)
- Carefree DOE (3 pages)
- 20_PV_I (32 pages)
- BOILERS (48 pages)
- MPO Series (4 pages)
- V8H Series (2 pages)
- SM-6 (28 pages)
- SCG (92 pages)
- CHG (4 pages)
- ALPINE (8 pages)
- MULTI-PASS (108 pages)
- C4 SERIES (2 pages)