Burnham 8H User Manual

Page 12

background image

2

M.

Attach Flame Roll-out Switch to Burner Access Panel.

See Figure 6. Flame Roll-out Switch and hardware

are located in Combination Boiler Parts and Control

Carton. Flame Roll-out Switch is a single use device

- do not test with heat - switch cannot be reset.
1. Cut insulation from semicircular notch at right

end of the burner access panel. Models 808H

- 810H have two (2) burner access panels. Remove

insulation from notch of right side burner access

panel only.

2. Attach Flame Roll-out Switch Mounting Bracket to

burner access panel with (1) #8 x ½” lg. sheet metal

screw.

3. Attach Flame Roll-out Switch to mounting bracket

with (1) #8 x ¾” lg. sheet metal screw.

N.

Install Burner Access Panel(s). Locate Burner Access

Panel(s) in Combination Boiler Parts and Control

Carton. Engage Burner Access Panel holes with

projections on Base Front Panel. See Figure 5.

O.

Install Immersion Well(s).

1. Remove Immersion Well(s) from Combination

Boiler Parts and Control Carton..

2. Insert Immersion Well in Tapping D. See Figure 3.
3. If second limit or operating control is used, insert

immersion well in Tapping E. If vertical gas

piping is to be installed inside of boiler jacket, it

is recommended that second limit be installed in

system piping.

P.

Install Jacket. See Figure 8.

1. Locate four (4) Jacket Attachment Brackets in

Combination Boiler Parts and Control Carton.

Attach to Front Base Panel and Rear Base Panels

with #8 sheet metal screws. See Figure 5.

2. Hang Left Side Panel and Right Side Panel onto

Jacket Attachment Brackets.

3. Attach Lower Rear Panel to Left and Right Side

Panels. Do not tighten sheet metal screws.

4. Attach Upper Rear Panel to Lower Rear Panel. Do

not install three (3) upper screws.

5. Remove Rating Label from envelope marked

“RATING LABEL ENCLOSED”. Remove

Combustible Clearance Label from Combination

Boiler Parts and Controls Carton. Attach to

Vestibule Panel in locations shown.

6. Attach Vestibule Panel to Left Side and Right Side

Panels.

7. Attach Lower Front Tie Bar to Left Side and Right

Side Panels.

8. Engage Upper Front Panel in slots on Left Side

and Right Side Panels. Place Top Panel in position.

Attach Top Panel to Left Side, Right Side and Upper

Rear Panels.

9. Tighten all jacket screws.

10. Affix Lighting/Operating Instructions Label and

Wiring Diagram Label to inside of Front

Removable Door. Labels are located in

Combination Boiler Parts and Control Carton.

Q.

Install Junction Box. See Figure 8. Attach junction

box to inside of Left Side Panel with ¼” - 20 x ¼” lg.

machine screw (located in Combination Boiler Parts

and Control Carton).

R.

Install Limit Control. Locate limit in Combination

Boiler Parts and Control Carton. Insert limit probe

into left immersion well as far as possible. Tighten set

screw.

S.

Install Auxiliary Limit or operating control (if used).

Insert control probe into right immersion well as far as

possible. Tighten set screw.

T.

Install Gas Control Assembly. Refer to Section III,

Gas Control System Assembly (Knockdown Boilers).

U.

EP and OP System: See Figure 9.

1. Install pre-wired EP/OP Control Cabinet Assembly

to right front corner of jacket top panel.

2. Install Honeywell RM7890 Control (located in

RM7890 Control Carton).

3. Remove RM7890’s Dust Cover. With a pair of side

cutters, carefully snip both wire leads to the brown

resistor labelled “JR2” and discard it. Replace Dust

Cover.

4. Install Honeywell R7847 Flame Amplifier.
5. Install heat shield.