D.

Install Drain Valve in rear of Left End Section,

Tapping “G”. See Figure 19. Components are located

in Water Trim Carton.

E.

Install Temperature-Pressure Gauge. Components

are located in Water Trim Carton.
1. Standard Temperature - Pressure Gauge Piping. See

Figure 20.

Figure : Drain Piping Installation

Figure 22: Recommended Piping for Combination

Heating & Cooling (Refrigeration) System

a. Install 2” NPT x 10” lg. nipple with gauge

tapping into Supply Tapping “A”. See Figure 3.

Gauge tapping should face forward.

b. Insert Temperature-Pressure Gauge. Tighten

by applying pressure to square shank on back

of gauge. DO NOT APPLY PRESSURE ON

GAUGE CASE since this may ruin gauge

calibration.

2. Alternate Temperature-Pressure Gauge Piping. See

Figure 21.
a. Install 2 NPT x 10” Nipple into Supply Tapping

“A”. See Figure 3.

Figure 20: Temperature-Pressure Gauge

Installation

Figure 2: Alternate Temperature-Pressure Gauge

Installation

b. Install 2 NPT x ¾ NPT x 2 NPT Tee (provided)

or 2 NPT x 2 NPT x ¾ NPT Tee (installer

furnished). ¾ NPT leg should face forward.

c. Install ¾ NPT x ¼ NPT Bushing.
d. Insert Temperature-Pressure Gauge. Tighten

by applying pressure to square shank on back

of gauge. DO NOT APPLY PRESSURE ON

GAUGE CASE since this may ruin gauge

calibration.

F.

Connect system supply and return piping to boiler.

See Figure 23. Also consult I=B=R Installation and

Piping Guides. Maintain minimum ½ inch clearance

from hot water piping to combustible materials.
1. If boiler is used in connection with refrigeration

systems, boiler must be installed with chilled

medium piped in parallel with heating boiler using

appropriate valves to prevent chilled medium from

entering boiler. See Figure 22. Also consult I=B=R

Installation and Piping Guides.