This inspection must:
1.

consider the service history of the aerial platform in terms of hours of service,
severity of use, and number and variability of users;

2.

review the inspection and maintenance record of the aerial platform;

3.

verify the efficiency of all operating controls;

4.

perform a visual inspection of the aerial platform;

5.

consider recommendations of the manufacturer regarding the aerial platform,
including manufacturer’s safety bulletins.

E – MAINTENANCE

Before adjustments and repairs are started on the aerial platform, the following precautions
must be taken:

1. The power system must be stopped, and the starting devices must be rendered inopera‑

tive;

2. All controls must be in the OFF position and all operating systems must be secured

against accidental activation by brakes, chocks or other means;

3. Elevating and rotating assembly and platform must be completely lowered, if possible,

or otherwise secured by blocking or propping;

4. The hydraulic oil pressure must be released from all hydraulic circuits before loosening

or removing hydraulic components;

5. Safety props or latches must be installed where applicable;
6. Other precautions must be adopted as specified in the user and operation manual.