Cable ladders for overhead wiring across rows – American Power Conversion PDU User Manual

Page 32

background image

Installation Procedures: Install Shielding Troughs, Shielding Partitions, and Cable Ladders

24

150kW InfraStruXure System—Installation and Start-Up

Shielding Partitions.

There are two types of Shielding Partitions, each of which forms a side wall

of a trough for data cables. You can customize the width of the trough for each row of your
system — wider for rows carrying many data cables, narrower for rows carrying fewer.

Cable Ladders for overhead wiring across rows

After installing the Shielding Troughs and Shielding Partitions, install the Cable Ladders between
rows of enclosures. You can also run Cable Ladders across Shielding Troughs in the same row, using
the hardware provided in the ladder kit.

Use wide Cable Ladders 12 inches (305 millimeters) where many power cables or data cables will
run between rows; use narrow Cable Ladders 6 inches (152 millimeters) where few power cables or
data cables will run between rows.

The Cable Ladders are 116 inches (2946 millimeters) long. You can adjust the length of the Cable
Ladders in the following ways:

• Cut the ends with a hacksaw to shorten them.
• Insert the connectors only partially into the side rails to extend them.

• As the back wall, use a Shielding Partition that

contains an opening for routing data cables.

• As the front wall, use a solid Shielding Partition to

hide data cables for a clean appearance.

See also

For more information on installing the Cable Ladders see the instruction sheet included
with the cable ladders (990-1576).

Note

Do not change the spacing between rows or the length and position of the Cable
Ladders from the layout you planned with your APC representative when you placed
your order. For overhead wiring, each PDU power cable is provided at a pre-determined
length. Changes to the physical configuration of your system could cause some PDU
power cables to be too short or too long.