Basic installation procedure – American Power Conversion PDU User Manual
Page 19

150kW InfraStruXure System—Installation and Start-Up
11
Basic Installation Procedure
This section provides the basic steps that you need to perform when installing InfraStruXure power
and rack components. Follow the references provided with each step for detailed instructions.
1. Unpack the components according to the unpacking instructions included on the outside of the
packaging or in the component’s manual.
2. Determine the correct placement of your system components by studying your InfraStruXure
Configure-To-Order (CTO) report. Move the InfraStruXure PDU and NetShelter VX
Enclosures to their final location.
3. Level the PDU and NetShelter enclosures, using the 13/14-mm wrench included with each unit.
4. Join adjacent NetShelter enclosures.
5. Ensure total power off.
6. Connect the power source to the PDU.
A licensed electrician must connect the power source.
7. Connect an EPO switch to the PDU monitoring unit.
Warning
Do not begin installing your InfraStruXure system without an APC Field Service
Engineer present.
Note
Search all boxes and packaging to make sure that they are empty before
discarding.
Warning
If installing InfraStruXure on a raised floor, make sure that the
raised-floor structure has a lb/in² rating that will support the full
weight of the InfraStruXure installation. See “Weight Considerations”
on page 7.
See page 13 for detailed instructions.
See also
For instructions on joining adjacent NetShelter VX Enclosures, see the
installation manual included with your enclosures.
See page 33 for detailed instructions.
See page 14 for detailed instructions.
See page 18 for detailed instructions.