Site Planning: Basic Installation Procedure
12
150kW InfraStruXure System—Installation and Start-Up
8. Install Shielding Troughs, Shielding Partitions, and Cable Ladders.
9. Install the Rack Automatic Transfer Switches (ATS), Rack Power Distribution Units, and other
InfraStruXure rack-mount devices.
10. Route and attach power cables to each Rack ATS and/or Rack PDU.
11. Route and attach communication cables to the InfraStruXure Manager hub (or switch).
12. Start the system.
Only qualified, APC-trained personnel may perform a system start-up.
13. Configure the InfraStruXure Manager.
See also
For instructions, see the manuals included with your Shielding Partitions,
and Cable Ladders.
See also
For instructions, see the manuals included with your Rack Automatic
Switches (ATS), Rack Power Distribution Units, and other InfraStruXure
rack-mount devices.
See page 26 for detailed instructions.
See page 32 for detailed instructions.
See page 33 for detailed instructions.
See also
For instructions, see the manual included with your InfraStruXure
Manager.