3.4 Mechanical installation for large version

Mounting the UP rail

Mounting the UP rail

Mounting the UP rail

Mounting the UP rail

INFORMATION!
You need a calculator, measuring band and pen & paper to install a large version.

CAUTION!
Make sure that you mount the rail parallel to the pipe. Mount the fixing units and the cable box as
shown below.

Figure 3-4: Mounting the large rail

1 Align the UP rail with the pipeline.
2 Fixing units
3 Turn screws clockwise to secure.
4 Mark the position.
5 Cable box