High Temperature Combustion

Installation/Startup

Teledyne

Analytical

Instruments

25

3.4 Inserting Reactor into Furnace

Carefully insert the Reactor Assembly into the Furnace and secure

the Assembly by following the procedure outlined in Figures 3-5
through 3-8.

 Finger-tighten the Gas/Liquid Separator (P/N: G608) to Reactor,

as shown below in Figure 3-5.

Figure 3-5: Gas/Liquid Separator


 Connect the Combustion Module Drain port to a facility gravity

drain with a 1 inch air break between the end of the drain line
and any liquids in the collection vessel (jar, facility drain) in
order to prevent a “vapor lock”. This drain line should be routed
in a straight fashion and free of kinks or restrictions thereby
allowing the liquids to drain freely.

 Prepare the Gas/Liquid Separator by filling it with D.I. water

until it overflows to drain, as shown in Figure 3-6. This provides
proper sealing of the reacted sample gases.