Install toe boards – Grain Systems Bucket Elevtors, Conveyors, Series II Sweeps PNEG-1842 User Manual
Page 61
8. 42" Head Platform Left Hand Drive
PNEG-1842 42"-48" Bucket Elevator Platform and Ladder “X” Series
61
Install Toe Boards
1. Install the longest toe board assemblies (HSP42015X and HSP42016X). Orient so that the
(HSP42015X) faces towards the down-leg end of the lower head.
2. Fasten toe boards to the support channels using 5/16" x 1" flange bolts (S-7440) and 5/16" flange
nuts (S-3611).
3. Install each end of the long “Z” toe board assembly to the bottom of the long toe board assemblies
using 5/16" x 1" flange bolts (S-7440) and 5/16" flange nuts (S-3611).
4. Install the “Z” toe board (HSP42037X) on the drive side at the down-leg end. Fasten to the ends
of the toe boards (HSP42015X and HSP42018X) using 5/16" x 1" flange bolts (S-7440) and
5/16" flange nuts (S-3611).
5. Install the “Z” toe board (HSP42036X) on the hatch side at the down-leg end. Fasten to the ends
of the toe boards (HSP42015X and HSP42018X) using 5/16" x 1" flange bolts (S-7440) and
5/16" flange nuts (S-3611).
Figure 8K