Installation (cont.), Installation guide power monitoring h81xx – Veris Industries H81xx SERIES Install User Manual

Page 7

background image

Z205338-0F

Page 7 of 10

©2013 Veris Industries USA 800.354.8556 or +1.503.598.4564 / [email protected] 09132

Alta Labs, Enercept, Enspector, Hawkeye, Trustat, Aerospond, Veris, and the Veris ‘V’ logo are trademarks or registered trademarks of Veris Industries, L.L.C. in the USA and/or other countries.

Other companies’ trademarks are hereby acknowledged to belong to their respective owners.

Installation Guide

Power Monitoring

H81xx

TM

10. H8163 and H8167: Set the Pulse Rate selection switch to the desired output rate (kWh per pulse). Note that 0.1 is not valid for

1600 A systems, and 0.1 and 0.25 are not valid for 2400 A systems.

N

A

+ A D + B D

+ C D

B

C

N

A B

C

+ - + - + -

Display

Plain

Full

Black

Black

Yellow

Yellow

Red

Red

1.0

0.5

0.25

0.1

11. Secure the meter cover shut using a padlock, wire tie, or other locking device.

12. Apply power to the meter.

13. Check the display. At initial power-up, the meter checks each phase. If the phasing is correct, an OKAY message appears. If

the phasing is incorrect, an error message indicates which color leads are not connected properly. Disconnect power before
reconnecting leads.

14. Check the power reading. Expected power is estimated as follows:

kW = Volts(L-L) * Amps * 1.732 * PF 1000

kW = horsepower * 0.746

15. To reset the kWh accumulator to zero, press and hold the two pushbuttons on the inside of the meter cover for 10 seconds.

16. To reset the kW max. register, press and hold the two pushbuttons on the inside of the meter cover for 5 seconds.

Installation (cont.)