beautypg.com

Figure 17 - integral safety loop – Motorola PTP 400 Series User Manual

Page 53

background image

51

Figure 16 - Mounting to pole diameters 25mm (1”) to 50mm (2”)

When adjustment is complete tighten all bolts to 14Nm (11 lb ft).

Warning:

Do not over tighten the bolts as bracket failure may occur.

The enclosure and mounting brackets of the PTP 400 Series Bridge are capable of

withstanding wind speeds up to 150mph (242kph). The installer should ensure that the

structure to which the bridge is fixed is also capable of withstanding the prevalent wind

speeds and loads. See Section 12 “Wind Loading”.

The integral safety loop should be used both for hoisting the ODU up a mast or building and

into position, and also as a fixing point to secure a permanent safety lanyard from the

tower/building to the ODU in case of mounting failure.

Figure 17 - Integral Safety Loop