Installation, Ms series inverter/charger (front view), Battery bank – Magnum Energy MS Series User Manual
Page 24

©
2012 Magnum Energy, Inc.
Page 15
Installation
Figure 2-4, DC and Battery Temperature Sensor Wiring
DC System Grounding point
[Electrode Conductor
(i.e., ground busbar)]
MS Series
Inverter/Charger
(front view)
Battery Temp Sensor Cable*
Inverter’s DC Negative Busbar
Inverter’s DC Positive Busbar
Inverter’s Equipment Ground Wire
BTS
BTS
MMP enclosure – for single inverter installations
(includes DC disconnect breaker, DC shunt for
battery monitor, and inverter DC busbars). If
multiple inverters will be installed, see the MP
enclosures - designed to allow up to four
inverters to be connected together.
Battery Bank
Battery Bank’s Equipment Ground Wire
Battery Bank’s Negative Cable
Battery Bank’s Positive Cable