10  Recommissioning the Inverter

Installation Manual

WB3-5TL-21-IA-en-10

57

10 Recommissioning the Inverter

If you have disconnected the inverter from voltage sources (e.g. for configuration purposes) and want
to re-commission it, proceed as follows.
Requirements:

☐ The AC miniature circuit-breaker must be correctly rated.
☐ A rectifier and overvoltage protection must be installed between the inverter and the plant.
☐ The inverter must be correctly mounted.

1. Connect the rectifier to the inverter:

• Connect the positive connection cable to the

front positive DC connector of input A on the
inverter.

• Connect the negative connection cable to the

front negative DC connector of input A on the
inverter.

☑ The DC connectors click audibly into place.

2. Seal all unused DC inputs using the DC connectors

with sealing plugs.