7  Commissioning

SMA Solar Technology AG

52

Ersatzstrom-IS-en-30

Installation - Quick Reference Guide

Procedure:

1. In the distribution board, switch on circuit breaker F1 and residual-current device F2.
2. Commission the PV system (see PV inverter documentation).
3. On the Sunny Island, press and hold the "On" button until you hear

an acoustic signal. This starts the system.

4. Only when two SMA Energy Meters are installed in the local network, assign the grid feed-in meter and purchased

electricity meter to the Sunny Island using Sunny Explorer. To do this, enter the serial number of the grid feed-in meter

and purchased electricity meter (see the Sunny Explorer user manual).

5. Open Sunny Portal via www.SunnyPortal.com/Register and run the PV System Setup Assistant. The required data

for registration in Sunny Portal must be at hand.

6. Activate the automatic update of the Sunny Home Manager and the PV system in Sunny Portal.
7. Only in systems with active power limitation, ensure that the limitation of the active power feed-in is configured and

functioning in Sunny Portal ("Configuring Active Power Feed-In Limitation", see the User Manual

"Sunny Home Manager in Sunny Portal" at www.SunnyPortal.com).

7.8 Commissioning a System Without Increased Self-Consumption

Requirement:

☐ The functionality of the automatic transfer switch must be checked (see Section 7.2, page 44).

Procedure:

• Commission the PV system (see PV inverter documentation).
• To start the system, press and hold the "On" button on the

Sunny Island until an acoustic signal sounds.

Representation of the Sunny Island inverters in Sunny Portal
In Sunny Portal, the Sunny Island inverters are always displayed as one device, even if the system consists of

three Sunny Island inverters. If there are three Sunny Island inverters, the data is added together.