SMA SI 3.0-11 Quick Reference Guide V.3.0 User Manual
Page 51

SMA Solar Technology AG
7 Commissioning
Installation - Quick Reference Guide
Ersatzstrom-IS-en-30
51
7.7.2 Commissioning a System With Increased Self-Consumption
Required data for registration in Sunny Portal:
Requirements:
☐ The basic configuration of the Sunny Island inverter must have been performed (see Section 7.1, page 40).
☐ The functionality of the automatic transfer switch must be checked (see Section 7.2, page 44).
☐ The Sunny Home Manager, the Sunny Island and all other Speedwire devices must be connected to the same router.
☐ DHCP must be enabled for the router of the system.
☐ The router of the system must have an Internet connection.
Deactivation of the intermediate storage of PV energy during certain charging procedures
To increase the service life of the battery, the system regularly carries out full charges and equalization charges
(see Technical Information "Battery Management" at www.SMA-Solar.com). During this charging process,
the intermediate storage of PV energy is deactivated and electricity may have to be purchased to perform the full
and equalization charges.
Device/customer data Required data and explanation
Sunny Home Manager
• Serial number (PIC) and registration ID (RID)
Register the new system in Sunny Portal using the PIC and RID.
SMA Energy Meter
• Only when two SMA Energy Meters are installed, note down the serial number and
purpose (e.g., PV production meter) in each case. This way you can identify the energy
meters in the Sunny Portal.
PV inverter
• PV system password
The PV system password is the same as the device password for the user group
"Installer". All devices in a PV system must be set to the same password (for user groups
and security concept, see the Sunny Explorer user manual).
The default password is 1111.
• Serial number of the PV inverters
You can uniquely identify the PV inverters in the Sunny Portal using the serial number.
• PV array power in kWp
SMA radio-controlled
socket
• The serial number and connected load of each SMA radio-controlled socket
In Sunny Portal, configure the SMA radio-controlled socket in accordance with the
requirements of the connected load. To do so, you require the serial number of the
SMA radio-controlled socket.
Customer data
• E-mail address
• Password for Sunny Portal access
• Address of the PV system
• Electricity tariff data
– Electricity price for purchased electricity
– Tariff times, if applicable (e.g., for tariffs with peak and off-peak tariff)
– Feed-in tariff
– Self-consumption tariff, if applicable