beautypg.com

3 connecting the master – SMA SI 3.0-11 Quick Reference Guide V.3.0 User Manual

Page 26

background image

4  Battery Backup Systems With All-Pole Disconnection

SMA Solar Technology AG

26

Ersatzstrom-IS-en-30

Installation - Quick Reference Guide

4.2.3 Connecting the Master

Figure 8: Connecting the master

Position

Designation

Description/information

A

Cable for the control voltage Sunny Island: connection AC1 Loads/SunnyBoys terminals L and N

Automatic transfer switch: connection X5 terminals L and N
Conductor cross-section: 2.5 mm² to 16 mm²

B

AC power cable

Sunny Island: connection AC2 Gen/Grid terminals L, N

TT

,

and PE

Automatic transfer switch: connection X3 terminals L1, N, and PE
Conductor cross-section: 10 mm² to 16 mm²

C

Measuring cable for voltage

measurement

Sunny Island: connection ExtVtg terminals L and N
Automatic transfer switch: connection X4 terminals L1 and N
Conductor cross-section: 1.5 mm² to 2.5 mm²

D

DC+ cable

Battery connection
Conductor cross-section: 50 mm² to 95 mm²
Cable diameter: 14 mm to 25 mm

E

DC − cable

F

Measuring cable of the

battery temperature sensor

Sunny Island: BatTmp connection
You only have to connect a battery temperature sensor if lead-acid

batteries are used.
Mount the battery temperature sensor in the middle of the battery

connection, in the upper third of the battery cell.

This manual is related to the following products: