Mhtc reflow plumbing – Nortec MH Series User Manual
Page 27
Installation | 24
MHTC Reflow Plumbing
Figure 22: MHTC Flow / B Plumbing Installation
On the MHTC reflow connect the drain pan’s drain to the hydraulic unit’s drain pan
connection using 2 in. (51 mm) ID hose cuff (provided).
Install a P Trap on the drain pan’s overflow. 6 in (15 cm) in height or duct static pressure + 2
in. whichever is greater.
Install a P Trap on the drain line from Reflow hydraulic unit. 6 in (15 cm) in height or duct
static pressure + 2 in. whichever is greater.
If spray bar elbow(s) are longer than required remove them from spray cap, cut to desired
length, and reinstall. Connect to staging valves through openings in back of unit.
Install spray bar lines ensuring hose has no dips or sags which could trap water.
A pressure equalization line is required between the hydraulic units reservoir and the duct to
ensure proper drain operation. Install a 3/8 in. (9.5 mm) port on the duct wall downstream
of hydraulic unit. Connect to reservoir with hose ensuring hose has no dips or sags which
could trap water.