beautypg.com

Testing – Gasboy CFN Series SCII Installation Manual User Manual

Page 84

background image

05/28/03

5-1

Section 5

TESTING


COMPLETION CHECK LIST


The information below should be reviewed to help verify proper installation of the CFN System
prior to testing the pumps and/or remote dispensers in the manual override position.

1.

Are the CFN system components located in the proper environment as described throughout
Section 2?


2.

Is there adequate clearance around the island card reader(s) (See Section 2, Island Card
Reader
)?


3.

Is all the wiring in metal conduit except as noted in Section 3, Short Haul Modem - RS-422
section?


4.

Is the AC and DC wiring in separate conduits, troughs, etc.? If not, and AC and DC wires
share conduit, shielded cable must be used as specified in Section 3 Communication
Requirements, RS-485
, Short Haul Modem - RS-422, or Section 4, Pulser Wiring and
Configuration
.


5.

Are the CFN system components on a separate dedicated breaker (see Section 3)?


6.

Are the CFN system components grounded properly (see Section 3)?


7. Are pumps over 3/4 HP at 120/240 VAC or 1-1/2 HP at 240 VAC equipped with a starter

relay (Section 4)?


8.

Is the correct gauge wire installed for the:

system (Section 3)?

pumps (Section 4)?

remote dispensers (Section 4)?

pulsers (Section 4)?

short haul modems (Section 3)?


9.

Are the communication lines under the maximum allowable distance:

RS-232 100 feet (Section 3)?

RS-485 1000/1500 feet (Section 3)?

RS-422 (short haul modems) 1500 feet (Section 3)?


10. If the system has an external modem, is the phone line installed (Section 3)?

11. Is there fuel in the tanks?