beautypg.com

Section 2: mechanical installation, 1 pre-installation checklist, 2 support structure requirements – Daktronics GPR-12EV-RGB User Manual

Page 9: Section 2, Mechanical installation, Pre-installation checklist, Support structure requirements

background image

Mechanical Installation

3

Section 2:

Mechanical Installation

Read the mechanical, power, and signal installation sections before installing the display(s).

Daktronics' engineering staff must approve any changes that may affect the weather-tightness of the

display. Detailed drawings of the changes must be submitted to Daktronics for evaluation and

approval, or the warranty may be void.

Daktronics is not responsible for installations or the structural integrity of support structures done by

others. The customer must ensure a qualified structural engineer approves the structure and any

additional hardware.

2.1 Pre-installation Checklist

Verify the following before installation:

The display is in good condition after shipping and uncrating.

A straight and square mounting frame is provided for the display.

Height variation in any 4-ft. (1.2 m) horizontal section must not exceed

1

/

4

" (6.3 mm).

Adequate support is provided for the display so that the structure will not yield at

any unsupported points after mounting.

Leave 4 inches (10.2 cm) of unobstructed space above the display so the eyebolt can

be removed.

No clearance is required once the eyebolt is removed.

Maintain clearance around the display to allow unobstructed air flow through the

vents and fans and to allow access to internal components.

Assure the display cabinet has no holes (accidental or intentional) that could allow

water to enter the display.

Check that all display modules are fully latched into the display cabinet.

2.2 Support Structure Requirements

The installer must ensure the mounting structure and

hardware can support the display, and that the structure

follows all local and national structural codes. Support

structure design depends on the mounting method,

display size, and weight.

Because every installation site is unique, no single

procedure is approved by Daktronics for mounting

GalaxyPro

®

Revolution displays. This section contains

general information that may or may not be appropriate

for this particular installation. Refer to Figure 2 and

Figure 3 for basic display setups.

Figure 4: Display Ventilation

This manual is related to the following products: