Controls – Installation / Setup / Commissioning
COMMISSIONING CHECK LIST
G
ENERAL
All equipment ordered by the customer is installed.
The unit is level and secure.
The mains and control wiring are complete and the circuit breaker and GPO are turned ON.
All Controller functions for the appliance operate.
All electrical or gas connections are to manufacturers specifications and the relevant electrical or gas
standards and codes.
U
NIT
–
D
UCTED
H
EATING
Electrical polarity of the power outlet is correct.
Heater is installed away from sources of dust and fumes (i.e. pool chlorine/petrol etc).
Gas leaks checked for, none present.
Flue outlet pipe complies with limits given / code and is sealed waterproof.
Combustion air meets requirements (internal, under floor).
Fan speed set is correct.
Burner pressure is correct.
Mounting pad/platform complies with requirements / codes.
U
NIT
–
D
UAL
C
YCLE
R
EFRIGERATED
A
IR
C
ONDITIONING
Unit Foundation correct
All pipe work is welded and vacuumed down.
Condenser Coil is purged before charging.
System is charged, all joints checked and pressures set correctly
Condenser unit is level
All clearances around the condenser set to manufacturers specifications.