Ground drive deferred item, Install high rate boom – Great Plains YP Fertilizer System User Manual
Page 14
Great Plains Mfg., Inc.
14
Fertilizer System
407-197M
02/29/2008
Refer to Figure 26
73. Slip the end of the hose onto the inlet elbow
(not
visible in photograph) and secure with clamp
74. Working back toward the tanks, use cable ties to
secure hose every two feet or so leave ample slack
for folding an unfolding. Do not tie the last four feet of
hose.
75. Leaving ample slack (but no so much that hose
droops below inter-tank tees), cut hose to length and
secure to tee with clamp
Ground Drive Deferred Item
The hose to the relief valve is installed after the starter
boom system, at “Pump to Starter Relief Valve Hose”
on page 17.
Install High Rate Boom
This section installs most of the components of the 407-
137A kit.
Install the high rate boom first, as it contains components
necessary for installing dual booms.
These instructions presume that the high rate (H.R.)
boom is to be connected to a customer-supplied fertilizer
source, typically a tractor-mounted tank. Tank, strainer,
pump, power source and supply line to the planter are
customer-provisioned and installed.
The high rate boom is presumed to be concentrated fertil-
izer that cannot be applied directly to the seed furrow. The
most likely delivery method is via tubes to zone coulters
at the front of the rows.
Figure 26
Supply Hose At Strainer
27098
2