Rockwell Automation 1771-TCM TEMPERATURE CONTROL User Manual
Page 35

4–8
Configuring the Modules
Publication 1771Ć6.4.5 - January 1997
To move a module from one project to another:
1. At the Module Manager screen, select the module you wish to
move.
2. From the
Edit menu, select Cut.
3. Close the Module Manager screen.
4. From the Project Manager screen, open the destination project (or
create a new project).
5. From the
Edit menu, select Paste into new.
The New Module dialog box appears.
6. Fill in the information in the dialog box and click on
OK.
The new module will be added to the module list.
7. Go to each configuration screen for the destination module, view
the pasted data, make any required changes, and then download
to the PLC processor, to a file, or to both to save the pasted data.
To save all configuration parameters, you must do this from the
Module Configuration, Loop Configuration, Tuning
Configuration, and Tuning Results screens, since each of these
screens downloads (or uploads) only the parameters shown on the
particular screen.
From the Loop Configuration, Tuning Configuration, and Tuning
Results screens, you can simultaneously download all eight loops
at once by using the Module Download command.
To learn how to configure the loops of the temperature control
module, read chapter 5.
Moving a Module From
One Project to Another
What to do next