Rake detail – Metal Sales Image II Installation User Manual
Page 26
© Metal Sales Manufacturing Corporation / Subject to change without notice, effective 6/2011
26
Rake Detail
1. Roof panel must be installed before Rake flashing.
2. If the panel ends off module, bend flat part of the panel up a
minimum of 1", otherwise skip to the next note.
3. Apply a row of Double Bead Tape Sealant to the flat part of the
panel next to the panel rib or vertical field bent leg.
4. Position and install Cleat to wall with #8-18 x
3
/
4
" Truss Head
Woodscrew, 1' o.c. Make sure Cleat installation allows for
proper Rake attachment.
5. Install Rake by sliding the open hem onto the Cleat and then
attaching to the flat pan of the Image II panel with #9-16 x 1"
Woodscrews, 1' o.c.
6. If two or more flashings are required, lap the flashing over
the previously installed flashing by a minimum of 2" placing a
bead of Tube Sealant between the flashings and securing with
Pop Rivets, 2" o.c.
Image II Panel (1)
Rake (5)
Truss Head Woodscrew,
1' o.c. (4)
Cleat (3)
Double Bead Tape Sealant (2)
Moisture Barrier
Optional Rake
with 1" Z-Closure
#9-16 x 1" Woodscrew,
1' o.c. (6)
(X) Numbers indicate sequence of installation.