Panel installation – Metal Sales Image II Installation User Manual
Page 22
© Metal Sales Manufacturing Corporation / Subject to change without notice, effective 6/2011
22
1. Field notch and hem the Image II panel as shown on page 20.
Apply a single bead of Tube Sealant inside the open hem of the
Image II panel.
2. Place the second panel on top of previously installed panel so that
the second hemmed panel can be engaged with the Offset Cleat.
3. Begin snapping the panels together working from eave to peak. It
is critical that panels only be snapped in one direction.
4. Repeat notes 2 and 3 for remaining panels.
5. Once installation is complete, fill each lower end of panel rib with
sealant. Also, clean any debris and excess sealant. Panels may also
be field notched and bent to close off panel end (See below).
Step 2
Concealed Fastened Panel Installation
Installing Second Panel
Panel Installation
Offset Cleat
Apply sealant at all
rib ends along eave
(2)
Position panel to keep
ends flush (1)
1"
1
1
/
2
"
1
1
/
2
"
Field cut panel ribs
1
/
2
"
Note: If you are to field bend the panel ends to close off panels on
the low side, this must be done before hemming of panels (see page
20).
Pop Rivet
(5)
(X) Numbers indicate sequence of installation.