Panel installation – Metal Sales Image II Installation User Manual
Page 18
© Metal Sales Manufacturing Corporation / Subject to change without notice, effective 6/2011
18
Step 1
Exposed Fastened Panel installation
Installing First Panel
Panel Installation
1. Apply a row of Double Bead Tape Sealant on the top leg of the
Eave flashing.
2. Install first panel so that the panel end has proper overhang
making sure that panel is square to eave and rake. It is critical
that the first panel be straight and square with the building as
it controls alignment of the following roof panels.
3. Fasten panel to substrate with a #8-18 x
3
/
4
" Truss Head Wood-
screw in center of the fastening groove located along the male
leg of the panel. Fastener spacing must be designed to meet
local building codes. It is important that the fastener be placed
in the center of the fastening groove and make sure not to over
tighten screws.
4. Fasten Image II panel with (4) #9-16 x 1" Woodscrews through
Double Bead Tape Sealant, flashing, and into the solid sub-
strate as shown below.
Square panel at Rake (2)
Position panel at Eave (2)
#9-16 x 1
"
Woodscrew (4)
Double Bead Tape Sealant (1)
Truss Head
Woodscrew (3)
CAUTION
Additional screws
may be required for
high snow loading
and steep slopes.
Image II Panel (2)
Double Bead Tape Sealant (1)
#9-16 x 1" Woodscrew (34)
(X) Numbers indicate sequence of installation.