Allied Telesis AT-8326GB User Manual

Page 51

background image

AT-8326GB Installation Guide

51

3. Slide the GBIC module into one of the GBIC slots in the front of the AT-

8326GB switch. The GBIC module is completely seated in the slot
when it clicks into place.

Figure 25 Installing a GBIC Module

4. If you purchased two GBIC modules for the switch, repeat this

procedure to install the second module.

Note
In order to use a GBIC module in Port 25 or 26, you must configure
the port in the management software to operate as a GBIC port and
not as a twisted pair port. For instructions, refer to the AT-S41
Management Software User’s Guide
. When you change the port
setting in the management software to GBIC, the GBIC connector
LED to the right of the GBIC slot will turn green.