Installation – Sterlco ST500 Series Central Granulator User Manual

Page 27

background image

27

INSTALLATION

SECTION 3-1

Uncrating the Granulator

OVERVIEW

This section deals with the procedures required to place your ST500 Series Granulator into service

after you receive it at your plant. The following basic steps need to be accomplished.

Uncrating the machine

Accounting for all necessary parts

Inspecting for damage and reporting any damage to the carrier

Cleaning the protective coating from the machine

Moving the machine to its service location

Checking and, if necessary, adjusting mechanical parts before applying electrical power

Connecting electrical power to the machine control panel and hydraulic

cylinder/jackscrew control panel located on the machine

Performing the start-up procedure

PLEASE FOLLOW THESE STEPS, AS OUTLINED TO ACHIEVE A SAFE AND

SUCCESSFUL START- UP OF YOUR T500 SERIES GRANULATOR.

The machine weights for the AT500 Series Granulators are as follows: ST5070 10000 pounds

ST5090 12500 pounds

ST50120 16000 pounds

UNCRATE THE GRANULATOR

As shipped, the granulator and the hopper are securely bolted onto separate skids and covered

with a wooden crate. The electrical cabinet, an optional item, is similarly packaged when ordered.

Remove the strapping.
Remove the packages and parts from the skid or inner sides of the crate. Remove the hold-

down bolts, nuts, etc.

Inspect for damage during transit and notify the carrier immediately of any damage.
Check the packing list and notify STERLING if there are any shortages.