4 assembly order – FlexLink WL322 (322 мм) Монтаж User Manual
Page 8
![background image](/manuals/329521/8/background.png)
About this manual
4
5683EN-1
1.4
Assembly order
The following list can be used as a checklist during your conveyor assem-
bly work:
Activity
Check
Cut all beams into suitable lengths
Connect feet and structural beams
Mount conveyor beam support brackets
Assemble conveyor beams and mount
them on to the support structure
Mount drive and idler units to the ends of
the conveyor
Mount slide rail on to the conveyor beam
Loosen the drive unit slip clutch
Run a short piece of chain through the
conveyor to check that there are no
obstructions
Assemble and mount the chain on to the
conveyor
Mount guide rail, drip trays and other
accessories on to the conveyor
Tighten the slip clutch to a suitable fric-
tion
Read Final preparations at the end of
this manual