Attaching the a-frame to the eave bracket, Chapter 7: roof assembly – Grain Systems Tanks PNEG-4135A User Manual

Page 130

background image

Chapter 7: Roof Assembly

A

A-frame rafter assembly

C

1/2 x 1-3/4 in. flange bolt (S-10252)

B

Center collar (CTR-0347)

D

1/2 in. flange nut (S-10253)

Attaching the A-Frame to the Eave Bracket

Assemble the lower portion of the A-frame rafters to the sidewalls.

1. Install flange bolts (B) and flange nuts (D), securing one side on the A-frame assembly.

2. Repeat this procedure for the other side of the A-frame.

3. Tighten to the recommended torque specifications. See

Bolt Torque Specifications, page 26

.

Figure 7-41 Attaching the rafter to the eave bracket

A

A-frame rafter assembly

D

1/2 in. flange nut (S-10253)

B

1/2 x 1-3/4 in. flange bolt (S-10252)

E

Hole for alignment tool

C

Eave bracket (CTR-0550)

After You Finish
Continue to the next A-frame installation until all of the A-frame rafter assemblies are installed. See

About

Temperature Cable Brackets and A-Frame Assemblies, page 83

.

130

Pneg-4135A 135 Ft Diameter 40-Series Bin