beautypg.com

Chapter 7: roof assembly – Grain Systems Tanks PNEG-4135A User Manual

Page 117

background image

Chapter 7: Roof Assembly

Figure 7-29 Assembling the short center collar channels to the long center collar channel

C

1/2 x 1-3/4 in. flange bolt (S-10252)

I

Long center collar channel (CTR-0278)

E

1/2 in. flange nut (S-10253)

J

Short center collar channel (CTR-0280)

G

1/2 x 1-3/4 in. flange bolt (S-10252)

K

Short channel clip (CTR-0329)

H

1/2 in. flange nut (S-10253)

22.Align the two center cap plates (L and M) onto the center collar channel assembly, ensuring the

center cap plates are parallel to the long center collar channel (I).

23.Apply a strip of tube caulk (N) along the inside edge row of holes as shown.

24.Install a splice plate (O) over the fresh strip of caulk (N), and install twelve bolts (P) and nuts (A)

securing the cap plates (L and M) and the splice plate (O)

Pneg-4135A 135 Ft Diameter 40-Series Bin

117