beautypg.com

Check-out procedure – Weil-McLain 550-141-826/1201 User Manual

Page 28

background image

SERVICE TECHNICIAN ONLY — read and follow completely.

Check off steps as completed

Boiler and heat distribution units filled with water?

Automatic air vent, if used, opened one full turn?

Air purged from system? Piping checked for leaks?

Air purged from oil piping? Piping checked for leaks?

Flue cap in place and tightened? Burner door closed, sealed

and nut tight? Burner plugged in and service switch on?

Obtain gas-tight seal to prevent possible flue gas

leakage and carbon monoxide emissions, leading

to severe personal injury or death.

Proper draft and burner flame? Final adjustment made with

combustion test equipment?

Test limit control: While burner is operating, move indica-

tor on limit control below actual boiler water temperature.

Burner should go off while circulator continues to operate.

Raise setting on limit control above water temperature and

burner should re-ignite.

Test additional field-installed controls: If boiler has a low

water cutoff, additional high limit or other controls, test

operation as outlined by the manufacturer. Burner should be

operating and should go off when controls are tested. When

controls are restored, burner should re-ignite.

Limit control set to system temperature requirements (max.

220°F)?

For multiple zones, flow adjusted to distribute heat in all

zones?

Thermostat heat anticipator setting (if available) set properly?

Refer to “Connect wiring,” page 22.

Boiler cycled with thermostat? Raise to highest setting and

verify boiler goes through normal start-up cycle. Lower to

lowest setting and verify boiler goes off.

Observed several operating cycles for proper operation?

Set room thermostat(s) to desired room temperature?

Completed Installation and Service Certificate below?

Reviewed pages 1–7 with owner or maintenance person and

instructed person to keep for future reference?

Returned all instructions provided with boiler to its envelope

and placed with boiler for future reference?

Check-out procedure

Date Installed: ____________________________

Boiler Model Number: _______ Series: ____________

CP Number(s): ___________________________

Measured Btu or GPH Input: ________________

Installation instructions have been followed.

Check-out procedure has been performed.

Above information is certified to be correct.

Information received and left with owner/maintenance

person.

Installation and service certificate

Installer: ________________________________________________________________________________________________

(Company)

(Address) (Phone)

_________________________________________

(Installer’s Signature)

Part number 550-141-826/1211

28

GOLD

WGO

OIL-FIRED NATURAL DRAFT WATER BOILER — SERIES 3 —

Boiler Manual