Install SpectraLink 6000 System
Survey Site
Check the site to be sure pre-installation work has been completed
correctly. This includes:
Location chosen for the MCU is adequate, and power is available.
Wiring to Base Station locations has been pulled and correctly
terminated.
Phone lines for the SpectraLink 6000 Wireless Telephones are
installed and properly terminated.
Dedicated line is available for remote access to diagnostic modem.
Telephone system administrator is on-site to program the existing
telephone system.
If the work has not been completed, the Polycom field service
engineer can leave the site and reschedule the installation when the
items have been completed or corrected, or assist in preparing the
site.
This unit must be installed by a service person familiar with the
installation of electronic equipment.
Do not power up the unit before it has been properly grounded to a
protective earth. See Grounding instructions below.
5
- SpectraLink SCE408 SpectraLink SCT416 SpectraLink 1725-36097-001 SpectraLink SCA516 SpectraLink SCK416 SpectraLink SCA408 SpectraLink SCJ408 SpectraLink SCI416 SpectraLink SCN416 SpectraLink SCO416 SpectraLink SCJ416 SpectraLink SCO408 SpectraLink SCS416 SpectraLink SCI408 SpectraLink RCC400 SpectraLink SCK408 SpectraLink SCL408 SpectraLink RCU201 SpectraLink SCA416 SpectraLink SCL416 SpectraLink MOG400 SpectraLink SCM416 SpectraLink SCC408 SpectraLink SCC416 SpectraLink SCD416 SpectraLink SCF416 SpectraLink SCN408 SpectraLink SCE416 SpectraLink SCF4089 SpectraLink SCX416 SpectraLink SCD408