Polycom recommends UL-listed wire that conforms to the following

specifications for AWG, distance, and number of power pairs

required for this installation.

Power

Pairs

Max Cable

Feet

22 AWG

Max Cable

Feet

24 AWG

Max Cable

Feet

26 AWG

1

6,000

3,800

2,400

2

N/A

6,000

4,800

3

N/A

N/A

6,000

One additional pair is also required for Data.

For wire runs of less than 3,500 feet, attenuation must not exceed
6.8 dB/1,000 feet at 772KHz.
For wire runs between 3,500 and 6,000 feet, attenuation must not
exceed 4.5 dB/1,000 feet at 772KHz.

Wire that is already installed (spare house cable) can be used when it

is available. House cable will usually run from the MDF in the

telephone equipment room to intermediate distribution frames (IDFs)

spread throughout the facility. Install new wire from the closest IDF

to the Base Station. Be sure no bridge taps, multiples, or “Y”

connections are created or present.
Determine the amount of wire needed to connect the Base Station to

the MCU by scaling from a floor plan or a sketch, pacing, measuring,

or estimating. Remember to include enough wire to reach the ceiling.

The wire length between the MCU and each Base Station may not
exceed 6,000 cable feet.

Install an extra 25 feet of wire at the Base Station to allow for
possible relocation.

Pull cable

Pull the cable from the MCU location (usually in the telephone

equipment room) to the Base Station locations designated on the floor

plans.

If the cabling exits the building, refer to Chapter 6, section Install
Outdoor Base Stations
.