Before installing an RMP, be sure you have prepared the UPS according to the

instructions in Chapter 2.

To install a Supervisory Contact Module:

1.

Securely mount the SCM.

2.

Install wiring from the SCM using ½-in. conduit through the

7/8-

in. knockout in

either the top or bottom of the UPS cabinet.

The top entry connection requires installation of ½-in. flexible conduit within the

UPS. Bottom entry connection requires no additional routing of conduit within

the UPS.

3.

If not already installed, locate the RMP adapter cable assembly (see Figure 14)

in the spare parts kit. Mate the DB---9 connector on the back of the terminal

block into the DB---9 connector on the Communications Panel of the UPS (see

Figure 15). Use two screws from the spare parts kit to secure the terminal

block bracket to the Communications Panel.

Connect to

Port 1 (DB---9) on

Communications Panel

TERMINAL

BLOCK

FUSE

(TB3)

Figure 14. Terminal Block Bracket