Prepare boiler – Lochinvar KNIGHT XL 801 User Manual
Page 13

2
Prepare boiler
13
Remove boiler from wood pallet
1. After removing the outer shipping carton from the boiler,
remove the parts box.
2. Remove the front door to access the lag bolts in front of
the unit (FIG. 2-1).
3. To remove the boiler from the pallet (after removing the
front door):
a. Remove the two lag bolts from the wood pallet 
 
inside the boiler (FIG. 2-1).
b. Detach the boiler from the lag bolts in the rear of the 
 
unit, see FIG. 2-1.
Do not drop the boiler or bump the jacket 
on the fl oor or pallet. Damage to the boiler 
can result.
For a boiler already installed, you must 
turn off gas supply, turn off power and 
allow boiler to cool before proceeding. 
You must also completely test the boiler 
after conversion to verify performance 
as described under Start-up, Section 10 
of this manual. Failure to comply could 
result in severe personal injury, death, or 
substantial property damage. 
For the 400 Model you must install a 
propane orifi ce to operate the Knight XL 
on propane gas. Verify when installing that 
the orifi ce size marking matches boiler size 
(Model 400 - 8.0 LP orifi ce stamping).
Models 501 - 801 do not require an orifi ce 
installation for propane operation, but 
they will require a valve adjustment. 
. 2
Figure 2-1 Boiler Mounted on Shipping Pallet
Gas conversions
NOTICE
ƽ WARNING
BLOWER
O-RING
VENTURI
SCREWS
QTY. 3
GAS VALVE
BRASS ORIFICE
O-RING
SCREWS
QTY. 4
Figure 2-2 Installing Propane Orifi ce - Model 400
Model 400
1. Remove the top and front access covers from the unit (no
tools required for removal).
2. Remove the three screws securing the venturi to the blower.
Note: When separating the venturi from the blower, take 
care not to damage the O-ring inside the blower (FIG. 2-2).
3. Remove the four star-drive screws securing the gas valve to
the venturi (FIG. 2-2).
4. Locate the propane orifi ce disk from the conversion kit bag.
Verify that the stamping on the orifi ce disk matches the 
boiler size (Model 400 - 8.0 LP orifi ce stamping). 
5. Remove the existing orifi ce from the O-ring in the side of the
gas valve and replace it with the orifi ce from the kit. Position 
and secure the orifi ce in the valve as shown in FIG. 2-2.
6. Reposition the gas valve against the venturi and replace the
star-drive screws (FIG. 2-2) securing the valve to the venturi.
7. Inspect the O-ring inside the blower. Handle the O-ring
with care, do not damage. Reposition the venturi against the 
blower and replace the screws securing the venturi to the 
blower (FIG. 2-2).
8. After installation is complete, attach the propane conversion
label (in the conversion kit bag) next to the boiler rating 
plate. Attach the LP caution label (in the conversion kit bag) 
to the left side of the unit in the lower left corner.
9. Replace the top and front access covers.
ƽ DANGER
Model 400: Inspect the O-ring when the 
blower is disassembled. The O-ring must 
be in good condition and must be installed. 
Failure to comply will cause a gas leak, 
resulting in severe personal injury or death.
ƽ WARNING
After converting to LP, check combustion 
per the Start-up procedure in Section 10 
of this manual. Failure to check and verify 
combustion could result in severe personal 
injury, death, or substantial property damage.
Installation & Operation Manual