Operational checks, Testing, Operational checks -6 testing -6 – Kodak RP 50 2J0686 User Manual
Page 80
Maintaining the Equipment
4-6
October 2002
Operational Checks
Check that the crossover assemblies and transport assemblies in the processor
are installed correctly and operating smoothly.
After performing all daily maintenance and before you begin to print jobs, run a
control strip to ensure that the processor is calibrated. See “Processing a Control
Strip” on page 3-32.
Testing
Before running the daily production jobs, run a control strip through the processor
and plot a graph of the results to determine if the equipment is operating properly.
See “Processing a Control Strip” on page 3-32.
If mottle (roller sock images) appears on the prints:
1.
Check the levels of the chemicals in the processor tanks. If necessary, adjust
the levels of the chemistry.
2. Operate the processor drive for 30 minutes to allow the roller socks to
become saturated with chemistry.