beautypg.com

Vent clearances and framing, A. pipe clearances to combustibles, B. wall penetration framing – Heat & Glo Fireplace Heat & Glo Fireplace 6000C User Manual

Page 39

background image

Heat & Glo • 6000C, 6000C-IPI, 8000C, 8000C-IPI • 2164-900 Rev. T • 9/12

39

A*

B*

10 in.

12 in.

C

D

10 in.

12 in.

A. Pipe Clearances to Combustibles

WARNING! Risk of Fire! Maintain air space clearance to

vent.

DO NOT pack insulation or other combustibles:

• Between ceiling firestops

• Between wall shield firestops

• Around vent system
Failure to keep insulation or other material away from

vent pipe may cause over heating and fire.

8

Vent Clearances and Framing

Figure 8.2 Wall Penetration

* Shows center of vent framing hole for top or rear venting. The center of the

hole is one (1) in. (25.4 mm) above the center of the horizontal vent pipe.

Figure 8.1 Horizontal Venting Clearances To Combustible

Materials

A*

B*

C

D

6000

in.

42-3/4

27-7/8

41-3/4

26-7/8

mm

1086

708

1060

683

8000

in.

44-3/4

29-7/8

44-1/8

28-7/8

mm

1137

759

1111

733

B. Wall Penetration Framing

Combustible Wall Penetration
Whenever a combustible wall is penetrated, you must

frame a hole for the wall shield firestop(s). The wall shield

firestop maintains minimum clearances and prevents cold

air infiltration.
• The opening must be framed on all four sides using the

same size framing materials as those used in the wall

construction.

• SLP pipe - A wall shield firestop must be placed on each

side of an interior wall. A minimum 1-1/2 in. (38 mm)

overlap of attached heat shields must be maintained.

• DVP pipe - A wall shield firestop is required on one side

only on interior walls. If your local inspector requires a

wall shield firestop on both sides, then both wall shield

firestops must have a heat shield (refer to Section 16.B.)

attached to them.

• See Section 10.M. for information for regarding the in-

stallation of a horizontal termination cap.

Non-Combustible Wall Penetration
If the hole being penetrated is surrounded by noncom-

bustible materials such as concrete, a hole with diameter

one inch greater than the pipe is acceptable.
Whenever a non-combustible wall is penetrated, the wall

shield firestop is only required on one side and no heat

shield is necessary.

* When using SLP or SL-D pipe, minimum clearances from the vent pipe to combus-

tible materials at inside wall firestops are: Top: 2-1/2 in. (64 mm)

Bottom: 1/2 in. (13 mm)

Sides: 1 in. (25 mm)

Note: Heat shields MUST overlap by a minimum of 1-1/2 in. (38 mm).

DVP heat shield - designed to be used on a wall 4 in. to 7-1/4 in. (102 mm to 184

mm)

thick.

• If wall thickness is less than 4 in. the existing heat shields must be field trimmed. If

wall thickness is greater than 7-1/4 in. a DVP-HSM-B will be required.

SLP heat shield - designed to be used on a wall 4-3/8 in. to 7-5/8 in. (111 mm to

194 mm thick).

• If wall thickness is less than 4-3/8 the existing heat shields must be field trimmed.

If wall thickness is greater than 7-5/8 in. a DVP-HSM-B will be required.

(DVP-SLP Pipe Shown)

3 in. (76 mm)

top clearance *

1 in. (25 mm)

clearance

bottom & sides

Heat

Shield

Wall

Shield

Firestop

Heat

Shield

WALL

3 in. (76 mm)

top clearance *

1 in. (25 mm)

clearance

bottom & sides

Heat

Shield

Wall

Shield

Firestop

Heat

Shield

WALL

3 in. (76 mm)

top clearance

1 in. (25 mm)

clearance around

vertical sections