Time Intervals for Maintenance Work

Maintenance work

Maintenance interval
(recommended)

Read out long-term data and error memory.

1 month *
(depending on system
size)

Clean or replace the filter material in the air inlet filters.

6 months *

Clean the insect guards at the air inlets and outlets.

6 months *

Clean the heatsink power module

12 months *

Check the inside of the cabinet and the EVR resistor for heavy dust deposits,
dirt, moisture, and water penetration from outside.
If necessary, clean the Sunny Central and employ suitable corrective
measures.

12 months

Check all power cable connections for looseness and tighten them if
necessary. Check the connectors and insulation for discoloration or
degradation. Replace any damaged connectors or corroded contacts.

12 months

Check adhesive warning labels and replace if necessary.

12 months

Cooling fans functionality test.
Check all cooling fans for functionality and operating noise. The fans can
be switched on by adjusting the thermostats, or during operation.
If present: cabinet fan, heatsink fan(s), internal circulation fan(s), diode fan,
heating fan

12 months

Heating functionality test.

12 months

Functionality test of all protective equipment present:

• leakage current circuit breakers
• line circuit breakers
• power switches
• motor overload switches

by means of manual activation or by pressing the test button (if applicable).

12 months

Visually check all fuses and disconnectors, and lubricate the contacts if
necessary.

12 months

Check overvoltage protectors.

12 months *

Check the 230 V und 24 V control and auxiliary voltages.

12 months

Overtemperature functionality test.
Check the overtemperature safety circuit.

12 months