SMA SB 1200 Installation User Manual
Page 26
Electrical Connection
SMA Solar Technology AG
26
SB12-17-IA-en-52
Installation Guide
13. Screw the threaded sleeve onto the socket element.
14. Tighten the pressure screw or cable gland tightly onto the threaded sleeve.
☑ The AC connection socket has been screwed together.
15. If the AC connection socket is not immediately connected to the inverter, close the AC socket on
the inverter with the protective cap provided.
16. Insert the AC connection socket into the AC socket
on the inverter. Remove the protective cap
beforehand as required.
17. Turn the threaded ring of the AC connection socket
tightly onto the AC socket on the inverter. The
threaded ring serves to seal and relieve strain on
the AC connection socket.
☑ The AC cable is now connected to the inverter.
Size used
Procedure
PG13.5
The fastening case along with the sealing ring is pressed into the threaded
sleeve and can no longer be seen.
PG16
• Retighten the lock nut of the
cable gland.
DANGER!
Danger to life due to high voltages in the inverter.
• Do not switch on the line circuit breaker until the PV generator has been connected
and the inverter is securely closed.