5 system registration in sunny portal, In sunny portal – SMA SPEEDWIRE V.1.6 User Manual

Page 23

background image

SMA Solar Technology AG

6  Commissioning

Installation Manual

SWWEBCONDM-IA-en-16

23

6.5 System Registration in Sunny Portal

6.5.1 Registering a Large-Scale PV Power Plant with

Cluster Controller in Sunny Portal

Requirements:

☐ The large-scale PV power plant must be commissioned (see Section 6.1, page 20).
☐ Your computer must have an Internet connection.
☐ The Cluster Controller must be connected to a router with Internet connection (see installation

manual of the Cluster Controller).

☐ JavaScript must be enabled in the web browser.

Procedure:

• In large-scale PV power plants with Cluster Controller, register in Sunny Portal via the user

interface of the Cluster Controller (see user manual of the Cluster Controller).

6.5.2 Registering a Small-Scale PV System in Sunny Portal

Requirements:

☐ The small-scale PV system must be commissioned (see Section 6.2, page 20).
☐ PIC and RID of the Speedwire/Webconnect data module must be available.
☐ Your computer must have an Internet connection.
☐ JavaScript must be enabled in the web browser.
☐ All UDP ports > 1024 on the router must be open for outgoing connections. If there is a firewall

installed on the router, you might have to adjust the firewall settings.

☐ It must be possible for the outgoing router connections to reach all Internet destinations (target

IP, target port). If there is a firewall installed on the router, you might have to adjust the firewall
settings.

☐ On the router with NAT (Network Address Translation), no port forwarding must be entered.

Potential communication problems can thus be prevented.

☐ There must be no packet filtering or manipulation for SIP packets installed on the router.

Maximum permissible number of devices for a small-scale PV system in Sunny Portal
In Sunny Portal, a maximum of four inverters with installed Speedwire/Webconnect data
module is permitted per small-scale PV system.