Working with the tnc 122 – first steps, Before you begin switch on the tnc – HEIDENHAIN TNC 122 User Manual User Manual

Page 15

background image

2

Working with the TNC 122 – First Steps

TNC 122

15

Working with the TNC 122 – First Steps

Before you begin

You must cross over the reference marks after every switch-on.
From the positions of the reference marks, the TNC automatically
re-establishes the relationship between axis slide positions and
display values that you last defined by setting the datum.

When you set a new datum point, the control automatically stores
the new relationship between axis positions and display values.

Switch on the TNC

2

Switch on the TNC and the machine tool.

0

1

M E M O R Y T E S T

P O W E R I N T E R R U P T E D

CL

N O C O N T R O L V O L T G

Clear the TNC message indicating that the power was interrupted.

The TNC automatically checks its internal memory.

Please wait...

I

Switch on the control voltage.
The TNC automatically checks the function of the EMERGENCY STOP button.

R E F T R A V E N T / N O E

Select reference mark evaluation.

ENT

R E F M A R K X Y Z

Press and hold:

Y

Z

X

Cross the reference marks in any direction:
Press and hold the machine axis direction button until the moving
axis disappears from the screen.
Sequence in this example: X axis, Y axis, Z axis

The TNC 122 is now ready for operation in the
MANUAL OPERATION mode.

If you do not wish to cross over the reference marks:

⇒ Answer the REF TRAV ENT/NOE dialog prompt with NO ENT

(this feature must be implemented by the machine tool
builder).