Operating Instructions

Primetest 220

14

8.3.6 To start the RCD test, press the button 9 .

8.3.7 The PrimeTest 220 will produce a test current of

30mA r.m.s. between the live and protective earth
of the supply. The test will commence at the start of
a positive half cycle.

8.3.8 The RCD will trip. The time taken to trip for the

positive half cycle, or the default time if no trip
occurred is displayed on the PrimeTest 220.

8.3.9 A flashing RCD time and displayed 7 indicates that

the RCD has failed to trip within 500ms.

8.3.10 Re-apply power to the PrimeTest 220 by resetting

the RCD and press the button 9 .

8.3.11 The PrimeTest 220 will produce a test current of

30mA r.m.s. between the live and protective earth
of the supply. The test will commence at the start of
a negative half cycle.

8.3.12 The RCD will trip. The time taken to trip for the

negative half cycle, or the default time if no trip
occurred is displayed on the PrimeTest 220.

8.3.13 A flashing RCD time and displayed 7 indicates

that the RCD has failed to trip within 500ms.

8.3.14 The RCD trip time will remain displayed until

another rotary switch or push button action.

8.4 IEC Lead TEST, IEC

See Figure 6.

8.4.1 Select the IEC test function on the rotary switch 10

Do not connect the IEC lead to the

PrimeTest 220, in preparation for an IEC lead

test, before the unit is switched on. Failure to

comply will result in an error message displayed

on the LCD.

PrimeTest 220 REV 1 5/12/05 1:52 pm Page 19