Operating Instructions

Primetest 220

10

8.0 Operation of test functions

8.1 Safety test, Class I

See figure 7

8.1.1 Select the Class I test function on the rotary

switch 10 . Ensure the IEC mains lead is
disconnected from the PrimeTest 220.

8.1.2 The LCD will display a probe signal to indicate that

an earth bond test lead is required. This test
function is selected when the equipment to be
tested is fitted with a protective earth conductor.

8.1.3 Plug the equipment under test (EUT) into the EUT

socket 11 on the front of the PrimeTest 220.

8.1.4 Plug the black test lead into the black socket 12 on

the PrimeTest 220.

8.1.5 Connect the other end of the black test lead to

exposed metalwork on the EUT.

8.1.6 To start a Class I safety test sequence, press the

button 9 .

8.1.7 The earth continuity resistance for the EUT is

measured at ± 200mA. The large display 2
indicates the highest digital earth resistance,

, the

small display 3 indicates a PASS/FAIL status. An
additional visual display of a ✓ or ✗ also indicates
the PASS/FAIL status.

8.1.8 Earth continuity resistance value is held on the LCD

display for a period of 1 second. A PASS or FAIL
indication will be shown, depending on value of the
displayed reading.

8.1.9 An earth continuity resistance that fails will

terminate the Class I PAT test, a PASS will
automatically sequence to the insulation resistance
test.

PrimeTest 220 REV 1 5/12/05 1:52 pm Page 15